Back to Projects
in 2011 we acquired 230 MWe Combined Cycle Power Plant in
partnership with Solar Power Netwroks kft and SIA kft. The
power plant is established on the basis of the following main
equipment:
GTE-160 type, 155 MW (ISO) gas turbine and its auxiliary
equipment (produced by LMZ of St. Petersburg, based on a
license concluded with Siemens company, out of the naturalized
components of V94.2 type). The GTE-160 possesses burners of
low emission; it meets the effective emission requirements.
TZFG-160 type air-cooled electric generator and
its auxiliary equipment (product of Elektrosila of St. Petersburg).
P-100 type heat recovery boiler and its auxiliary equipment
(product of Podolsk Machine Factory).
The heat recovery boiler has two pressure levels, is of forced
circulation system, has a vertical standing layout, with a metal
chimney on its roof.
By-pass stack between the gas turbine and the heat recovery
boiler (product of Podolsk Machine Factory).
KT-80-7.0 type condensation steam turbine with double-casing,
its auxiliary equipment (LMZ product).
TZFP-80 type air cooled electric generator and its auxiliary
equipment for the steam turbine (product of Elektrosila of St.
Petersburg).